Check
This step allows to verify and edit the analysis manually. The coverage thresholds are displayed as a reminder.
At the startup of the command, the 3D scene split in two views:
An overall view, called Progress View, displaying the whole project and where you can select a specific BIM part to inspect.
A detailed view containing detailed information about the current selected BIM part, if any.
In the dialog, a Result table lists all BIM part and some associated data such as the coverage score, current status and global offset (median value of the offset distribution).
Each time a new element is clicked in the table, the 3D views are updated. Press SPACE to change the current element status.
The table header columns can be sorted.Optionally, filter the visible parts according to their status.
Optionally, modify the parts Transparency to be able to see possible inner points. This transparency is temporary applied when checking the selected part.
Then click Next to validate and continue (Export).
Several shortcuts are available in from the 3D views:
Arrow Up/Dow to change the current selection in the Result table
H to toggle the visibility of the selected BIM part
Space to change the current element status